Step by step
STEP 1
Remove high spots, ensure clean, sound surface.
Apply primer where required.

STEP 2
Mix product in bucket.
DO NOT thin. After mixing use as is.
Coverage: 25 kg mixed product covers 6 m2 applied in 1 hour.

STEP 3
Apply Weber Gamatex with a steel trowel.

STEP 4
Float with a plastic trowel to either vertical or random pattern.
Drying time: Approx. 12hrs (surface dry = 2hrs, hard dry = 12 hrs ) depending on weather conditions (temperature and humidity).
Curing time (before sealing if required): 7 days to fully cure but sealing coat can still be applied after 12hrs when it is hard dry.

Coverage is approximately 5–6 m2 per 25 kg bucket (1 coat) at 2.5 mm thick (aggregate size less than 2.5 mm